Optimize Options

Key Concepts

This dialog is used to initiate a process of automatically reconstructing all (or part) of the schedule to improve its quality and incorporate all recent data updates into the schedule. The schedule optimization is performed based on the Optimize Settings that are configured from the drop-down menu of the Optimize tab.

There are two types of Optimize Settings to choose from:

  • Shared Scenario Settings: These settings are stored for each Scenario.  Using the Scenario Settings is usually the better option to use (rather than the "Personalize Optimize Settings" option) on a daily basis when there are multiple planners using the system. If each planner uses the Scenario Optimize Settings then you can be sure that everyone is Optimizing in the same way. Note that the Scenario Optimize Settings are also used by the Scheduling Agent when automated Optimizations are performed.
  • Personalized Optimize Settings:  These settings are stored separately for each User in order to retain each User's preferences.  These can be useful in performing What-If analyses or for general experimentation.

optimize

Setting Up the Optimize Settings

  • Optimize Activities Starting At: This specifies the starting point for the optimization and only activities that start after this specified time are included in the rescheduling. This feature is useful if the schedule must remain stable in the short term for shop floor logistics or other reasons. The following options are available:
    • Beginning of the Schedule
    • End of the Frozen Span
    • End of the Stable Plan Span
    • Specific Date/Time: When this option is selected, an additional field appears underneath where the user can set a specific date and time to start the optimization process.
  • Jobs to Exclude: Any Jobs that match the checked options in the Jobs to Exclude section will not be scheduled during the Optimize. If they were previously scheduled, then they will be unscheduled during the Optimize. This section gives planners control when choosing which Jobs enter the schedule. For example, a planner might want to only include Firm Jobs in the schedule as these are sure to be executed. However, a planner may also wish to see how the workload will be affected if Estimates, CTP, or Planned Jobs are included. Note: Individual Jobs can also be Excluded from the schedule by checking the Do Not Schedule option. Excluded Jobs are shown in the Excluded tab of the Jobs pane. The Exclude options are:
    • Planned: The Job’s commitment is planned.
    • New: The Job was newly created and never scheduled.
    • Estimates: The Job’s commitment is an estimate. (This includes Capable To Promise Jobs)
    • Unscheduled: The Job was previously unscheduled by a planner.
    • On-Hold: The Job’s On-Hold status is set to On-Hold. (A status of “Some Operations On-Hold” does not qualify). Note: if on-hold jobs are scheduled, then they will be scheduled to start after the Hold-Until Date of each operation.
  • Optimize Rule(s) to Use: This field specifies which sequencing rules to use during the optimization.
    • Use one Rule for all Resources: The optimize rule specified here will be used on all the resources during the optimization. This option can be used to easily experiment with different optimize rules without having to edit each resource`s rule.
    • Use Normal Resource Rules: Use each resource’s “Normal Rule” during the optimization. Normal Rules represent the normal set of optimize rules that are used for normal operation of the resource.
    • Use Experimental Resource Rules: Use each resource’s “Experimental Rule” during the optimization. Experimental rules are the set of optimize rules generally used in What-If scenarios as they provide a way to edit individual resource rules without losing the Normal Rule settings.

Note: The Normal and Experimental Rules can be modified by double-clicking on a resource on the left of the Gantt, and accessing the Optimization | Optimize Rules tab.

  • Release Rule(s) to Use: Each manufacturing order is prevented from scheduling until it is released. Release Rules determine how manufacturing orders are released for scheduling during an optimization and therefore supersede the optimize rules.
    • JIT with Resource HeadStart: Release dates for each operation are calculated to target a “Just in Time” completion of the Job/MO need date. The JIT Slack Days can be specified for each resource by double-clicking on the resource and changing the “Headstart Span” field of the Optimize tab. Each manufacturing order will be released based on the lead Activity’s JIT Start Date minus the HeadStart Span specified for each resource.
    • JIT with Global HeadStart: This option will enable a text box next to the drop-down menu where users can set the number of JIT Slack days to be applied to all resources. Each manufacturing order will be released based on the lead Activity’s JIT Start Date minus the JIT Slack specified.
    • Drum-Buffer-Rope: The DBR calculation are used to manage the release date for operations that have consistent capacity-constrained resources. Each manufacturing order is released based on its DBR Release Date minus the JIT Slack Days specified in the optimize settings.

Note: The greater the JIT Slack Days value, the earlier the manufacturing order can start.

  • Auto-Join Manufacturing Orders: If this is checked, then manufacturing orders with the same AutoJoinGroup that are scheduled consecutively in one capacity interval are joined during the optimization. This can be helpful in situations where releasing a single MO to the shop floor in a shift is preferred.

See also: MPS/MRP Process